- When installing laminate floors in large rooms make sure to place expansion joints every 13 m width-wise and every 13m length-wise. Also, it is preferable that you provide expansion joints between different rooms. They can be finished using moldings attached to the subfloors.
- Never allow the end joints of to successive rows to be in line by staggering them by at least 10 cm.
- We recommend you purchase a few extra cartons of flooring, which will come useful in case of damaged planks, miscalculation of the room and further repairs.
|
|
Preparing the room |
|
|
- Check that doors can still open after you install the underlayment and the floor
- Check to see whether the molding can be removed. The floor can also be finished with Quick Step profiles.
- The floor of the room should be flat. Please make sure you have smoothed out any unevenness.
- The subfloor must be clean and dry.
|
|
|
CONCRETE SUBFLOOR |
|
|
New construction: |
|
- Make sure to allow the new concrete floor to dry for a week if it is of 1 – 4 cm thick and the double amount of time for a thickness of over 4 cm.
- If you are installing the laminate flooring in a room with underfloor heating, make sure that the subfloor does not exceed the temperature of 28°C and that the moisture content is less than 1.5% and make sure to ask for special instructions or use a professional for the installation.
|
|
Renovation: |
|
- Remove any type of flooring (carpet, needle felt, etc)
- If the previous flooring is damp sealed (PVC, linoleum, VCT, etc.) you do not have to remove it.
- Make sure to always use underlayment. For optimal results, use Quick Step underlayment.
|
|
|
WOODEN SUBFLOOR |
|
|
- First remove any previous flooring
- Check to see whether the plank floor is stable and nail down any loose planks and use special leveling layers if necessary.
- The Quick Step planks must be installed crosswise to the direction of previous floors.
- Make sure that the crawl space under the laminate flooring has sufficient ventilation by removing any obstacles. The maximum moisture content of the wood must not exceed 12%.
|
|
|
Installing the floor |
|
|
Step 1 |
|
|
Install the Quick Step underlayment per width and as you progress. Before cutting it to size, let it run up the wall a bit.
As the first floor strip is affixed to the floor panel, the two other strips must be clicked into it. Slide the strip and cut the panel. See fig. 2-6
|
|
|